* Fuel is total fuel consumed as % of hourly consumption at peak output.
Output is % of peak output.
Start from Minimum Load
- Plant is operating with 7EA at 50% Load and only one steam turbine is on line.
- The LM 6000’s and second steam turbine have been down less than 12 hrs.
- The 7EA starts increasing load immediately.
- The first LM 6000 starts immediately and the others follow on one minute intervals.
- Steam turbine 1 follows steam production.
- Steam turbine 2 starts 10 min after 7EA begins to ramp.
- Duct burners start immediately after maximum unfired steam production is achieved.